The cleanup of the Gowanus Canal is advancing ahead of schedule, the US Environmental Protection Agency (EPA) announced at the Gowanus Canal Community Advisory Group (CAG) general meeting on Oct. 27.
According to Victoria Sacks, remedial project manager at the EPA, phase two dredging in the middle section of the canal—called Remediation Target Area 2 (RTA 2), which sits between Third Street and Hamilton Avenue—will commence in two weeks, almost two years ahead of schedule. Work will start even as some bulkheads are still being installed, Sacks told the CAG.
“They will be able to do about 58% of the phase two dredging in RTA 2 in this phase of work,” Sacks said, adding that work that should have started in June 2028 will now probably be complete in 2027.
She noted that while some might wonder about this piecemeal approach, “with this project, in order to move as fast as we can, we take what we can get.”
The CAG also said farewell to Brian Carr, lead attorney at EPA Region 2 and one of the key figures in making the Gowanus Canal a federal Superfund site—and stewarding the cleanup—who retired at the end of October after 32 years with the agency. Since he joined the Gowanus Canal project in 2008, Carr, who has an engineering background, has remained a voice of reason on the pollution in the neighborhood.
At Thomas Greene Park, where part of the Fulton Manufactured Gas Plant used to operate, the EPA is currently testing whether in-situ geochemical stabilization—a process in which a chemical solution is injected into the soil to immobilize underground contaminants—could be a viable remedy for the coal tar in the soil. Sacks told the attendees that, while the data has not been fully analyzed, “It looks like it went well.”
Once the data is in, the agency and its contractors will consider whether to move forward with field testing in the park itself, but Sacks could not provide a timeline for when that would take place or how long it would run.
In a follow-up email from the EPA, Press Officer Barbara Khan wrote that the EPA expects lab results this year.
A source of concern in recent months has also been the coal tar leaking into the water at the top of the canal, an area where the remediation technically is complete. At last month’s CAG general meeting, EPA reps shared that the agency’s original plan to mitigate the leak was ineffective and that a new solution was being worked on.
On Tuesday night, Sacks said that the EPA is still tweaking the new plan to make sure it works as intended, but that work should begin in November. The solution, while blocking the coal tar from entering the canal, does not address the contamination’s entry point to the canal.
“There’s a leak and we can’t find the hole,” Carr said.
Sacks also said the two combined sewer overflow (CSO) tanks, under construction by the New York City Department of Environmental Protection (DEP) under EPA oversight, are progressing as planned.
At the site of the larger tank, on Nevins Street at the top of the canal, below-ground demolition and repair are underway and about halfway complete; upcoming work like above-ground mobilization and pre-construction inspections are scheduled for mid-November, and will require periodic street closures.
Work at the smaller tank, which will sit near the top of Second Avenue, on the opposite side of the canal from Public Place, is still in the excavation phase. The digging has not caused harmful levels of odors, air monitoring around the site shows.
The New York State Department of Environmental Conservation (DEC) provided an update on its soil vapor intrusion investigation in Gowanus, which is likely entering its final year this heating season. A public meeting will be held Nov. 17, where DEC and the New York State Department of Health (DoH) will hold a joint presentation, Aaron Fischer, DEC project manager, told the CAG. The meeting starts at 7 p.m. and is held in PS 372’s gymnasium on 215 First St.
Fischer also said that every property within the Gowanus Canal area has received letters with the offer of having the building sampled for intruding soil vapor.
“If you or anyone you know live within these boundaries, or if you own a property within these boundaries, or are a tenant within these boundaries, please have them contact me,” Fischer said. He can be reached at [email protected] or (518) 402-9805.
DEC also shared that at the Con Edison Yard on Third Avenue, an investigation is still ongoing to determine the geographical extent of the contamination. The site, which has been in the state brownfield program since 2017, is located just next to PS 372, which currently is dealing with an unknown source of soil vapors.